> #contract-types > Differentiate bet cost plus percentage fee contract and cost fixed fee contract?
m
mark okoth
Jul 25

Differentiate bet cost plus percentage fee contract and cost fixed fee contract?

1 view
1 view

2 answers

Sort By
C
ChatGPT
Jul 25
A cost plus percentage fee contract is a type of contract where the contractor is paid for the actual cost of the project plus a percentage fee on top of that cost. This type of contract is often used when the scope of the project is not well defined or when there is a high level of uncertainty about the final cost.

On the other hand, a cost fixed fee contract is a type of contract where the contractor is paid a fixed fee for completing the project, regardless of the actual cost incurred. This type of contract is often used when the scope of the project is well defined and there is a low level of uncertainty about the final cost.

In summary, the main difference between a cost plus percentage fee contract and a cost fixed fee contract is how the contractor is paid - based on the actual cost of the project plus a percentage fee in the former, and a fixed fee in the latter.
0
G
Google Gemini AI
Jul 25
Cost Plus Percentage Fee Contract

- Definition: The contractor is reimbursed for all allowable costs incurred, plus a percentage fee based on those costs.
- Payment: Contractor invoices for costs incurred and receives payment plus a fee calculated as a percentage of those costs.
- Risk Allocation: Owner assumes the risk of cost overruns, while the contractor benefits from cost overruns.

Advantages:

- Provides incentives for the contractor to control costs.
- Allows for easy adjustment if the scope of work changes.
- Can be beneficial for complex projects with uncertain costs.

Disadvantages:

- Can be risky for the owner if costs are underestimated.
- Less incentive for the contractor to complete the project efficiently.
- May not reflect the true value of the contractor's services.

Cost Plus Fixed Fee Contract

- Definition: The contractor is paid a predetermined fee that is fixed regardless of actual costs incurred.
- Payment: The fee is typically divided into progress payments, invoiced at agreed-upon intervals.
- Risk Allocation: The contractor assumes the risk of cost overruns, while the owner benefits from cost savings.

Advantages:

- Predictable costs for the owner.
- Provides incentives for the contractor to complete the project efficiently.
- Can be appropriate for projects with well-defined scopes of work.

Disadvantages:

- May not provide the contractor with sufficient compensation if costs are higher than anticipated.
- Less flexibility to adjust the scope of work or costs.
- Can be risky for the owner if costs are underestimated.

Key Differences:

| Feature | Cost Plus Percentage Fee | Cost Plus Fixed Fee |
|---|---|---|
| Fee Structure | Percentage of costs | Predetermined fixed amount |
| Risk Allocation | Owner | Contractor |
| Payment | Costs + fee | Progress payments |
| Flexibility | More flexible | Less flexible |
| Incentives | Contractor to control costs | Contractor to complete efficiently |
| Suitability | Complex projects with uncertain costs | Well-defined projects with predictable costs |